Luna August 2009

  • Finalizare montat tamplarie PVC
  • Teste lift interior
  • Tencuieli interioare parter
  • Tencuieli interioare etaj 1 si 2
  • Executie termosistem latura nordica a imobilui
  • Finalizat instalatii electrice interior
  • Montat balustrade terase
  • Executie termosistem fatade N-V
  • Tencuieli interioare etaj 3
  • Executie izolatie rigips – acces lift